Purchase:..Raw materials.................N15,000
Finished goods.................N11,400
Stock:....(1/7/01)Raw materials..........N2,250
Work-in-progress...............N1,875
Wages:.....Direct...............N17,100
Indirect..............................N5,400
Stock:.....(30/06/02)Raw materials.......N3,000
Work-in-progress..............N3,375
The cost of raw materials consumed is?
N17,250
N15,750
N15,000
N14,250
Correct answer is D
No explanation has been provided for this answer.